The new Cedar Covered Bridge replica is complete!
(September 3, 2004)
|
 |
Final construction work on the Cedar replica.
(August 5, 2004)
|
|
|
The side sections of the Cedar Covered Bridge replica are set in position.
(June 24, 2004)
|
|
|
Another view showing the cross braces connecting the side sections. Note the new approach which will connect the bridge floor with the roadway.
(June 24, 2004)
|
 |
The bridge side structures are assembled on the work platform.
(May 21, 2004)
|
 |
 |
Work continues on the bridge understructure.
(January 14, 2004)
|
Setting the caissons to the correct elevation.
(January 13, 2004)
|
 |
 |
South approach pier piling finished.
(January 7, 2004)
|
Construction begins: Steel pilings are driven.
(December 22, 2003)
|
Bottom four photos courtesy of the Madison County Engineers office.
|